Lead Time: 25 Days vs 45 Days

Lead Time: 25 Days vs 45 Days

Realistic timeline

ScenarioProductionTotal from PO
Stock mould, natural colour20–25 days25–30 days
Stock mould, custom colour25–30 days30–35 days
New mould + plain25–35 days mould + 20–25 days production50–65 days
Stock mould + IML30–35 days35–42 days
New mould + IML55–70 days60–80 days

Add 3–7 days for booking, and 2–4 weeks of ocean transit depending on destination.

The five things that delay production

  1. Artwork approval circling for a week (most common)
  2. Deposit arriving after the PO
  3. Colour masterbatch not in stock
  4. Chinese New Year or National Day holiday cluster
  5. Carton printing ordered late — cartons are usually the last item and the first to delay

How to protect your date

  • Approve artwork before issuing the PO
  • Put a shipping window with a penalty clause in the contract for repeat orders
  • Book space 2 weeks before the planned ship date, not after production ends
  • Ask for a weekly production photo — cheap, and it surfaces problems early

FAQ

Is 15 days realistic? Only for stock items in stock colour, and only if there is machine capacity that week.

Does a larger order take longer? Yes, roughly linearly beyond 200,000 pcs.

Next step

Tell us the SKU and target ship date. We will tell you honestly whether it fits, and what would have to change if it does not.

Related reading

Models covered on this site: 2500 ml PF-RW2500 · 750 ml PF-RG750 · 750 ml PF-GG750 · see all models in this category.

Looking for a PP food container manufacturer?

We manufacture PP lunch boxes, bowls, compartment containers and sauce cups in Guangdong, China with OEM and IML printing service. Get a quote today.

Get Free Quote → Browse Products